The Role of Risk Assessment and Inspection Planning in Achieving Excellence in Pressure Equipment Integrity and Reliability

How to Put it All Together - Guide to Organizing a Successful PEI Program

By John Reynolds, Principal Consultant at Intertek. This article appears in the September/October 2010 issue of Inspectioneering Journal.
4 Likes
This article is part 5 of a 10-part series.
Part 1 | Part 2 | Part 3 | Part 4 Part 5
Part 6 | Part 7 | Part 8 | Part 9 | Part 10

 

Introduction

In the first article in this series entitled How to Put It All Together– Guide to Organizing a Successful PEI Program, (1) I provided an overview of the necessary Management Systems (MS) for a successful program to achieve excellence in pressure equipment integrity (PEI). This is the fifth article in that series. Clearly, Risk Assessment and Inspection Planning have a major role in achieving excellence in Pressure Equipment Integrity and Reliability (PEI&R). But there is a lot more to PEI&R than just Risk Assessment and Inspection Planning. This article will show how Risk Assessment and Inspection Planning plays a central role in PEI&R, but will also show how the management system (MS) for Risk Assessment and Inspection Planning must be integrated with 9 other important management systems shown in figure 1 in order to achieve excellence in PEI&R.

For purposes of review (or for those who did not see the original article in the Sept/Oct, 2009 edition of the Inspectioneering Journal (IJ), and in order to set the stage for this follow-on article, I will repeat, directly below, some of the same introduction included in the first article(1). The second article in the series covered Management Leadership and Support for PEI (4), and appeared in the Jan/Feb, 2010 edition of the IJ. The third article in the series covered Management of Change and Integrity Operating Windows for PEI(5), and appeared in the Mar/Apl, 2010 edition of the IJ. The fourth article in the series covered The Role of Corrosion Control in Achieving Excellence in Pressure Equipment Integrity and Reliability (6) appeared in the May/June, 2010 edition of the IJ. For those who would rather not review the introductory material, you can skip directly to the third section of this article which is labeled Risk Assessment and Inspection Planning.

Knowing what all needs to be accomplished in order to achieve excellence in PEI&R is one thing, but knowing how to organize it all for success is quite another. I have previously written/published numerous articles about what all needs to be accomplished (1-3). In this article I will show how to organize all 10 of the PEI&R MS to achieve overall success i.e. in order to make sure that everything that needs to be accomplished, is accomplished using management systems (MS) and work process (WP) descriptions. Without an effective organizational strategy for PEI&R, many of the 101 essential elements of PEI&R(2) can “drop between the chairs” because there may be no management system in place to make sure that each element is properly considered, planned, scheduled and completed at appropriate intervals by a responsible party. However with an effective PEI&R MS in place, each site should be able to maintain pressure equipment integrity (i.e. no breaches of containment) and to achieve pressure equipment reliability (i.e. having pressure equipment available to function as designed to meet the business plan), both of which comprise PEI&R excellence.

Speaking of excellence, Vince Lombardi, one of the most famous football coaches in the history of the NFL, once said “Perfection is not attainable, but if you chase perfection, you will catch excellence.” I believe that to be very true and especially when it comes to implementing an effective pressure equipment integrity program. But what is excellence in PEI&R? It’s not “gold plating” or overdoing or spending too much on the PEI&R program. It’s simply doing everything that needs to be done, doing it right, doing it when it needs to be done, in order to create, implement and sustain the PEI&R program to avoid breaches of containment. Keep that definition in mind, as I will refer to it often. Having effective management systems (MS) in place for all the PEI&R issues that need to be handled is the foundation for a successful PEI&R program.

But what is a management system? In my experience, it’s simply a compendium of all the necessary information that describes what must be done, why it needs to done, how it is to be done, and how often or when. Some operating sites then combine their PEI&R MS with PEI&R WP maps and descriptions to show who is involved and how the work flows, i.e. what comes first, next, last and in between plus what can be done in parallel and what must be done in series. Management systems are the input to the WP maps and descriptions. For the purpose of this article, I will concentrate on creating, implementing and sustaining the MS, but will mention how WP maps and descriptions are also needed to achieve efficiency and effectiveness in the PEI&R program.

Note: For those of you who are more accustomed to the term “mechanical integrity (MI)”, I use PEI&R throughout this article as somewhat of the equivalent of MI, but pertaining only to what I refer to as pressure equipment or what some others may refer to as “fixed equipment” or “stationary equipment”.

I recognize that there may be many ways to organize a PEI&R MS program for success, so I will present just one suggested way to do it, not the only way. Other ways to organize a PEI&R MS program may be equally effective, just as long as all necessary elements are included, scheduled and accomplished according to plan. This article is intended for those organizations that may not yet be achieving excellence in PEI&R (see above definition) and that believe perhaps the way they are organized (or even disorganized) may be part of the problem.

Without effective PEI&R MS, even if we know what needs to be done, we might be just “flailing at the wind”, as my grandmother used to say, rather than accomplishing what needs to be done effectively and efficiently to prevent beaches of containment.

The Ten PEI&R Management Systems

This content is available to registered users and subscribers

Register today to unlock this article for free.

Create your free account and get access to:

  • Unlock one premium article of your choosing per month
  • Exclusive online content, videos, and downloads
  • Insightful and actionable webinars
GET STARTED
Interested in unlimited access? VIEW OUR SUBSCRIPTION OPTIONS

Current subscribers and registered users can log in now.


Comments and Discussion

There are no comments yet.

Add a Comment

Please log in or register to participate in comments and discussions.


Inspectioneering Journal

Explore over 20 years of articles written by our team of subject matter experts.

Company Directory

Find relevant products, services, and technologies.

Training Solutions

Improve your skills in key mechanical integrity subjects.

Case Studies

Learn from the experience of others in the industry.

Integripedia

Inspectioneering's index of mechanical integrity topics – built by you.

Industry News

Stay up-to-date with the latest inspection and asset integrity management news.

Blog

Read short articles and insights authored by industry experts.

Expert Interviews

Inspectioneering's archive of interviews with industry subject matter experts.

Event Calendar

Find upcoming conferences, training sessions, online events, and more.

Downloads

Downloadable eBooks, Asset Intelligence Reports, checklists, white papers, and more.

Videos & Webinars

Watch educational and informative videos directly related to your profession.

Acronyms

Commonly used asset integrity management and inspection acronyms.