Equinor LNG Plant Broke Maintenance, Safety Protocols Ahead of 2020 Fire

Reuters, April 22, 2021
Reuters

Equinor must fix a series of rule breaches exposed by a fire at its Melkoeya liquefied natural gas (LNG) plant in Norway last year for the plant to reopen, the country’s safety watchdog said on Thursday. The September 2020 blaze shut down production at the plant, also referred to as Hammerfest LNG, and Equinor has said it could take until October to be repaired.

The serious breaches that we saw are related specifically to management and compliance to procedures ... and also to manning in the organization,” Anne Myhrvold, director of the PSA watchdog, told Reuters after presenting the investigation’s findings. Other deficiencies were related to risk analysis and filter maintenance, as well as the need for an overview of the emergency response resources, she added.

The fire broke out in the air intake of a gas turbine generator, the PSA said, where filters had likely auto-ignited after being clogged by insects. The filters had not been replaced since 2015, while Equinor had previously changed them every two years, it added.

No workers were injured in the six-hour blaze.

The watchdog ordered Equinor to ensure operations staff had access to the information needed to ensure safe operations, and to demonstrate the plant has adequate staffing and competence to deal with all conditions. The company must present a plan for complying with the orders by June 1 and address the issues raised before the plant can restart, the PSA said.

We take this incident very seriously... and we will respond in a thorough and timely manner,” Irene Rummelhoff, Equinor’s head of marketing, midstream and processing, told Reuters.

Rummelhoff added the company’s own investigation would look into why the filters had not been replaced earlier.

Europe’s only large-scale LNG plant, at Melkoeya island just outside the Arctic town of Hammerfest, can process 18 million cubic metres (mcm) of gas per day when fully operational. Gas is piped from the offshore Snoehvit field some 160 km (100 miles) away in the Barents Sea, which was also forced to shut as a result of the plant’s closure.

On Dec. 2, a fire in a compressor building shut down operations at Equinor’s methanol plant at Tjeldbergodden. The PSA is also investigating this incident but has not yet published its findings.


(Reporting by Nora Buli and Nerijus Adomaitis; Editing by Gwladys Fouche, Jan Harvey and Mark Potter)

Click here to read the full article from Reuters.

Copyright 2024 Thomson Reuters. Click for restrictions.

Comments and Discussion

There are no comments yet.

Add a Comment

Please log in or register to participate in comments and discussions.


Inspectioneering Journal

Explore over 20 years of articles written by our team of subject matter experts.

Company Directory

Find relevant products, services, and technologies.

Training Solutions

Improve your skills in key mechanical integrity subjects.

Case Studies

Learn from the experience of others in the industry.

Integripedia

Inspectioneering's index of mechanical integrity topics – built by you.

Industry News

Stay up-to-date with the latest inspection and asset integrity management news.

Blog

Read short articles and insights authored by industry experts.

Expert Interviews

Inspectioneering's archive of interviews with industry subject matter experts.

Event Calendar

Find upcoming conferences, training sessions, online events, and more.

Downloads

Downloadable eBooks, Asset Intelligence Reports, checklists, white papers, and more.

Videos & Webinars

Watch educational and informative videos directly related to your profession.

Acronyms

Commonly used asset integrity management and inspection acronyms.