Motiva Enterprises plans to finish shutting down the gasoline-producing unit at its 607,000 barrel-perday (bpd) Port Arthur, Texas, refinery on Monday to begin a planned overhaul of the unit, sources familiar with plant operations said.
Motiva began shutting the 81,000 bpd fluidic catalytic cracking unit (FCCU) on Sunday for a planned 50-day overhaul, the sources said.
Motiva declined to comment on Monday.
While the FCCU is shut for the planned 50-day overhaul, Motiva will also shut the 18,000-bpd alkylation unit and the 50,000-bpd cat feed hydrotreater for 30-day overhauls, the sources said.
(Reporting by Erwin Seba; Editing by Chizu Nomiyama)
Comments and Discussion
There are no comments yet.
Add a Comment
Please log in or register to participate in comments and discussions.